2012-06-18 scrum call

Attending

  • Benn
  • Marie
  • Heather

Items covered for this sprint

  • jira tickets listed here

Scruminess

  • What are you planning to do between now and the next call?
    • Marie - finish up the email stuff and get it out for review
    • Benn - more progress on the documentation of identifier assignments
  • Any impediments/stumbling blocks?
    • Marie - nothing in particular
    • Benn - nothing in particular

2012-06-20 e-scrum

Scruminess

  • What have you done since the previous call?
    • Marie - Fixed CO-359; Worked on backbutton (co-70), council delegates
    • Benn - Made some progress on CO-344, including yet another design overhaul; Reviewed demo script with Heather
  • What are you planning to do between now and the next call?
    • Marie - council delegates, ligo-stuff, and whatever comes back via email
    • Benn - More on CO-344; Review Marie's various emails
  • Any impediments/stumbling blocks?
    • Marie - waiting for emails
    • Benn -

2012-06-22 dev call

Attending

  • Benn
  • Marie
  • Heather

Items covered for this sprint

  • jira tickets listed here

Scruminess

  • What have you done since the previous call?
    • Marie - worked on plug-in, trying to figure out how to make various bits of COmanage to work with it; got back to Marie wrt Back Button and email stuff
    • Benn - much progress on CO-344
  • What are you planning to do between now and the next call?
  • Marie - vacation, other LIGO responsibilities
  • Benn - vacation
  • Any impediments/stumbling blocks?
    • Marie - the pluralization/singularization of names of things is being ignored in the plugin (discussed on call)
    • Benn - encountered some cake limitations that needed a workaround

Dev business

  • (end of month) - review of release dates - will do @ F2F in Milwaukee July 9-11
  • CO-360 and 361 (see email from Benn 06/21/2012)
  • No labels