Timeframe

Timeline: January 2011 - July 2011

Description

Phase 2 of the PEER project will oversee the development of the PEER project in coding 'sprints' and also put in place appropriate mechanisms to ensure that all elements of PEER integrate effectively and are well developed for potential users.

Work Areas


WORK AREA 1: PROJECT MANAGEMENT

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status

PM4: Management Liaison

Arrange biweekly calls between project management liaisons (NH, LJ, LL, LF)

No deliverable

No due date

NH / LJ

Ongoing

PM5: PEER Sustainability Model

Develop a proposal for PEER service sustainability

Report on sustainability

31/12/11

NH

Not started

PM6: PEER module integration

Provide oversight and documentation to support integration of PEER components

input to PEER documentation

31/07/11

LJ

Not started

PM7: Metadata aggregation and signing

Define a process for integrating with appropriate metadata aggregation and signing process, currently defined as out of scope for the PEER project

input to PEER documentation

31/02/11

LJ

Not started




WORK AREA 2: PEER SOFTWARE DEVELOPMENT

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status

PSD2: Metadata Registry

Development of a metadata registry for PEER

Registry software issued under appropriate OS license

31/07/11

Yaco

Not started

PSD3: PEER Interface

Development of appropriate user interface for PEER registry

template interface to be used with pilot PEER instances

31/07/11

Yaco

Not started

PSD4: PEER documentation

Full installation documentation for PEER

Documented processes on wiki

31/07/11

Yaco

Not started




WORK AREA 3: PLUGGABLE METADATA VALIDATOR

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status

PMV1: Pluggable Metadata Validator

Support to enable the development of a metadata validator up the priority list for the JISC consortium

12 days coding effort on validator

31/07/11

Shibboleth Consortium

Not started

PMV2: Validator documentation

Documentation as appropriate for the validator on the shibboleth wiki

Wiki documentation

31/07/11

Shibboleth Consortium

Not started




WORK AREA 4: SUPPORT AND DELIVERY

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status

SAD3: Advanced Use Cases

Develop more advanced use cases for PEER

Documented Use Cases

31/03/11

Wayf.dk

Complete

SAD4: PEER user documentation

User-friendly information about PEER and use of its metadata to support federations and other users

Documentation

31/07/11

Wayf.dk

Not started

SAD5: PEER promotion

Promotion of PEER at appropriate events

No deliverable, time can be claimed

ongoing

NH / LF

Not started