Timeframe

Timeline: October 2010 - February 2011

Description

The planning phase of the PEER project (PEER Phase One) will involvement the initial development of a proposed architecture for PEER, the development of initial use cases (to be refined), development of a project plan and management of funding and contractual arrangements for PEER.  

Work Areas


WORK AREA 1: PROJECT MANAGEMENT

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status

PM1: Secure PEER Funding

ISOC have agreed to provide funding for the PEER project, with TERENA
acting as a clearing house for project funds

Funding Letter from ISOC to TERENA      

12/12/10

LL

Complete

PM2: PEER Project Plan

Develop a full project plan for PEER

Project Plan 'live" on I2 wiki, hard copy delivered to TERENA

31/01/11

NH / LJ

In Progress

PM3: Contractual Arrangements

Using common TERENA contractual template, put in place contracts with YACO, EDINA, JISC Advance, WAYF.dk (Leif?)

Signed contracts with TERENA

28/02/11

LF

In Progress

PM4: Management Liaision

Arrange biweekly calls between project management liaisons (NH, LJ, LL, LF)

No deliverable

No due date

NH / LJ

Ongoing




WORK AREA 2: PEER SOFTWARE DEVELOPMENT

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status




WORK AREA 3: PLUGGABLE METADATA VALIDATOR
No work is scheduled under this work area for phase 1.



WORK AREA 4: SUPPORT AND DELIVERY

 

 

 

 

 

Work Item

Description

Deliverable

Due Date

Owner

Status