:width | =100% | |columnAttributes | =width=15%,width=85% | |
Dates | Task |
---|
By Feb. 1 | Finalize review team - Determine registries subgroup members, agree on review process. |
}
|| Dates || Task ||
| By Feb. 1 | Finalize review team - Determine registries subgroup members, agree on review process. |
| 2/1-2/8
| Agree on evaluation questions, set review taskforce meeting times
|
| 2/29 - 3/30
| Review ID Match options (review high level strawman proposal Benn already developed, evaluate [OpenEMPI\|http://openempi.kenai.com/] as option for OSIdM4HE ID Match, make recommendation about next steps (write new app, agree on strawman for high level)
|
| 3/30\- 4/15
| Agree on investment structure for ID Match
|
| 4/16\- 6/15
| Write ID Match code or develop reference implementation with
OpenEMPI
OpenEMPI\\ |
| 6/16 - 8/15
| Testing, bring up as parallel service at UCSF
|
| 3/30-4/15
| Plan investment structure for Registry
|
| 2/10 - 2/24
| PSU, OR, and KIM respond to evaluation questions
|
| 2/25 - 3/9
| Evaluation team reviews responses, generates more detailed questions to be addressed during code review
|
| 3/12 - 3/16
| Code review of PSU Registry
|
| 3/19 - 3/23
| Code review of OpenRegistry (Rutgers)
|
| 3/26 - 3/30
| Review KIM registry
|
| 3/31 - 4/15
| Develop Registry recommendation for OSIdM4HE |
{table-plus}