Registries Timeline

Dates

Task

By Feb. 1

Finalize review team - Determine registries subgroup members, agree on review process.

2/1-2/8

Agree on evaluation questions, set review taskforce meeting times

2/29 - 3/30

Review ID Match options (review high level strawman proposal Benn already developed, evaluate ´╗┐OpenEMPI\ as option for OSIdM4HE ID Match, make recommendation about next steps (write new app, agree on strawman for high level)

3/30- 4/15

Agree on investment structure for ID Match

4/16- 6/15

Write ID Match code or develop reference implementation with OpenEMPI

6/16 - 8/15

Testing, bring up as parallel service at UCSF

3/30-4/15

Plan investment structure for Registry

2/10 - 2/24

PSU, OR, and KIM respond to evaluation questions

2/25 - 3/9

Evaluation team reviews responses, generates more detailed questions to be addressed during code review

3/12 - 3/16

Code review of PSU Registry

3/19 - 3/23

Code review of OpenRegistry (Rutgers)

3/26 - 3/30

Review KIM registry

3/31 - 4/15

Develop Registry recommendation for OSIdM4HE