Summary

This document provides a breakdown of the work items in the “Gap Analysis” section of the community survey from the InCommon Certificate Service Review Working Group. Primarily, only those items receiving ‘high’ or ‘medium’ priority are listed, though there is a table that outlines those items with ‘low’ priority that are either done or are being pursued. The work items are categorized below by responsible party.

Subscriber Survey

The full report of the subscriber survey from the Certificate Service Review Work Group can be found here:

InCommon's Work Items

Medium Priority

 

Item

Status

Target

DCV documentation

Not yet started.

2017, Q4

EV documentation

Have started with new EV process at: https://spaces.at.internet2.edu/x/YAxhBg

2017, Q3

InCommon Cert API

Currently awaiting prioritization/scheduling within TIER

TBD

High Priority

 

Item

Status

Target

FAQ doc RE: how to get support

waiting on I2 ServiceNow KB system

2017, Q4

 

Comodo's Work Items

Medium Priority

 

Item

Status

Target

ACME Support

Comodo is waiting on maturity of the spec.

Pending discussions with Comodo

SmartCard Certificates

DONE

2016

Improve support function for EV process

Ref. ‘anchor certs’ project

2017, Q3?

Allow wildcard in CN with SANs

In 5.6 rel; 1/2017 ?

Pending discussions with Comodo

Bulk certificate management (both API and CCM)

 

Pending discussions with Comodo

Sync DCV expirations per-org

Done/coming soon?

2017?

 

High Priority

 

Item

Status

Target

Improve custom notifications (addl. fields, events, documentation)

 

Pending discussions with Comodo

Improve authentication options for API

 

Pending discussions with Comodo

Additional API fields/functions

 

Pending discussions with Comodo

CM/CA Status Page

  DONE

2017

Roadmap for support communications

Uncertain...

Pending discussions with Comodo

 

Shared Work Items (both InCommon and Comodo)

Medium Priority

 

Item

Status

Target

Single Initial POC for support

Not currently feasible

 

CCM Training

 

2017, Q2

Support webinars

Need to identify topics

ongoing

 

High P riority

 

Item

Status

Target

Stronger SLA

DONE

2016

SSO

In development

2017, Q2

MFA

In development

2017, Q2

Support KB, tailored for InCommon issues

Hope to use coming ServiceNow implementation at I2

2018, Q1

 

Work Items Receiving “low” Priority (yet which are being implemented)

 

Item

Status

Local CA options

Pending feasibility?, legal, communications

AD Integration

Basic functionality DONE

Better integration of vulnerability scanner

DONE