  1. Delivery of design and architecture 
    1. Discussion: Detailed design and architecture review 
  2. Delivery of code by end of August 30, 2013
    1. Discussion: Detailed code review outlining how the final code differs from the Design presented earlier.
  3. Community testing and bug fixing 
  4. Acceptance of code by December 1, 2013.## If the Acceptance Criteria have not been met by this date, Internet2 may extend this date at its sole discretion.
  5. Optional post-project support 

...