  • Email the Grouper-Users List asking for input
  • Ask for input at the face-to-face Grouper WG at 2012 SMM
  • Reach out to specific campuses asking for input
  • Schedule a webinar to discuss UI planning with the community
  • Ask the UI experts at U-Chicago for their input on the UI and also on the process of involving the community
  • Create a users group who to review the user interface as it is being developing

Consider chunking things into phases along these lines:

Date(s)

Activity

April 1 - May 31

Gather community requirements and requests in table above. Weekly reflection on grouper-dev list of new requests and any discussion of them. Counter proposals? Acceptable? Relative priority? Do others want to add their names as Requesters?

April 23

I2 SMM Grouper WG F2F

May 1

Float initial proposal for technology stack to be used to build v2.2 UI. Post to grouper-dev.

May 1-14

Drive discussion on grouper-dev of tech stack, with intent to settle as much of it as possible during this period.

May 18?

IAM Online focused on Grouper v2.2 UI planning & requirements

May 15

Float initial proposal for UX process to grouper-dev

May 15-31

Drive discussion on grouper-dev of UX process with intent to settle it during this period.

June 1-15

Finalize acceptance status of each request by grouper-dev and assign each to a priority class.